Saturday 6 December 2008

Health and Safety on the Chalcots

The low levels of light to the entrance ways and underground car parking continues to be a very considerable concern to all residents in the vicinity of the Chalcots.

The situation has been currently under review for some time. Irrespective of whether the properties are responsibility of the PFIC group of companies or ultimately the Local Authority. It must be remembered that the Local Authority is the primary "Social Landlord" and the "Landlord" for all properties. Under Health and Safety Protocols and Security provision Protocols have a direct "Duty of Care" not only to all residents but also all residents in the Belsize area that may be affected as a "knock-on consequence" of the above mentioned low levels of lighting provision and inadequate security.

Friday 5 December 2008

Common sense prevails at Camden's PFIC

I reported yesterday "if you (Camden) don’t have temporary lights installed by the end of the next day (4/12) then I will take the matter to the local MP". Glenda Jackson MP was contacted. Senior officers of Camden and the PFIC were instructed.

I had an "official" walk-about yesterday with all the senior staff connected with the PFIC so they could see first hand the problem areas.

As of 8:45am today I can report that Bray now has the emergency temporary lighting asked. All that remains is that a permanent solution is found for the lighting problems.

Thursday 4 December 2008

Strength of resident feeling on Chalcots "escalate"

I was present at an ad hock walk-about with an Camden Project Manager yesterday evening and on the subject of NO lighting on the entranceways to Bray, which has been a ongoing problem for many years.

A resident knowing the Project Manager clearly angered at the situation, said to the officer "if you don’t have temporary lights installed by the end of the next day (4/12) then I will take the matter to the local MP". The deadline set is now looming.

I have had so many complaints now from residents about this Health and Safety concern that MP Glenda Jackson has now been notified.

This is an outrage; even the local Police have reported the matter of inadequate lighting to the Patch Manager for the estate.

Wednesday 3 December 2008

Camden PFI Chalcots December 2008

Where we are now in December 2008

Bray, the third of the five blocks making up the Chalcots estate is due to be signed off by the Independent Certifier (IC) 19th December.However, problems still remain in resident’s homes, such as leaking radiators, faulty windows and poorly regulated central heating controls, despite the IC sign off process. All the remaining problems will be transferred to the "snagging" process.Security remains a "key" concern of the residents at Bray and indeed the whole of the Chalcots.Inadequate lighting and no provision of a canopy to the entranceways continue to be a BIG concern for all residents.

Back in July 2008
I had written a summary of the “key” problem areas of the PFI process

1. Output Specification
2. Role of the Independent Certifier (IC)
3. Sign-off and snagging
Only the misapprehension of the role of the IC has now been addressed.It was hoped that with the correct levels of “direct” management pressure would the other issues have been addressed too.

Conclusion
Apart from the previous misapprehension that the role of the IC was to actually check all aspects of the finished “home” and check for essential Health and Safety certifications. We now know that the IC primary role is to sign-off, thereby starting the “unitary charge” process for release of “real” money from the PFIC bank to the contractor.

There is no real demonstratable change of the current implementation model.
It has to be said that PR skills have considerably improved on this PFI project.

I would also now add a new key "problem" PFI and non-PFI word to the list;

4. Communications
This refers to both the PFIC as well as the Local Authority, which are in many cases the worst offenders.

Tuesday 2 December 2008

PFI at Chalcots - Third block due to complete


Bray, the third of the five blocks making up the Chalcots estate is due to be signed off by the Independent Certifier (IC) 19th December.

However, problems still remain in resident’s homes, such as leaking radiators, faulty windows and poorly regulated central heating controls, despite the IC sign off process. All the remaining problems will be transferred to the "snagging" process.

Security remains a "key" concern of the residents at Bray and indeed the whole of the Chalcots.

Inadequate lighting and no provision of a canopy to the entranceways continue to be a BIG concern for all residents.

Monday 1 December 2008

Offenders to wear community vests


Another crazy idea. How are the Public meant to distinguish between contractors, builders and offenders (without referring to the backs of the high visibility jackets or bibs).

If a person is seen fit to be returned to serve a "Community Service". Having a "Community Payback" will only serve to further distance the offender from mainstream society and may leave the offender open to abuse. This is back to the dark ages. http://news.bbc.co.uk/1/hi/uk/7757908.stm

Start of the 13 month 15% VAT Rate Today

But will it actually have the desired effect and who will profit?

Large e-companies (such as Amazon) clearly will have no problems implementing and passing on the lower rate to their customers. However, the "very type of smaller business" most affected by the credit crunch will have a much harder time to implement and pass on the savings in the high street.

The cost to small businesses to implement the VAT rate change will be high compared to turnover and it will be unlikely that the customer will see benefit at the till. A product or service that has been pitched at £9.99 will not be marked down to £9.77 for long.

The VAT rate change is a negative way of dealing with credit crunch; it serves to illustrate the despair that the New Labour Government is in.

It is back to the OLD Labour days of the past. History does indeed repeat itself

Sunday 30 November 2008

Schools in Belsize

There are currently no LEA nursery or primary schools in the Belsize ward, all local schools in the ward are "private" and places are in BIG demand. In neighbouring wards ALL LEA primary schools have a never ending waiting list. The Belsize ward has around 8000+ population of which the Chalcots alone represents nearly a "quarter". This is a major issue for all residents. There are good "Independent Private Schools " but with places also being in high demand and fees ranging upto £3795 per term, clearly is not an option for all residents.

PFI Not the way to go

http://news.bbc.co.uk/1/hi/uk_politics/7757130.stm

PFI IN CAMDEN – “The saga continues"

I have recently discovered members of the "PFIC - Partners For Improvement in Camden" do not include Camden.

This was believed to be the true:
http://www.internationallawoffice.com/deals/Detail.aspx?g=d4576c3f-25e4-da11-be7e-001143e35d55

But this actually is the true partner list:
http://www.partnershipsuk.org.uk/PUK-Case-Study.aspx?Region=London&SubRegion=Camden&Project=11978

PFI IN CAMDEN – “The Chalcot Experience”

History

PFI stands for Private Financing Initiative, the concept started for the first time in the UK back in 1992. I do not propose to go through a catalogue of success or failures of the concept here in this blog.

LBC has a very large portfolio of social housing stock with a mix of street properties of varying ages of around 90 years and 40 to 45 years for the concrete “estates” popular during the 1960’s.

In common with much of local authorities around the country these properties have not seen major refurbishment since having been built.

When government funding become available under the terms of PFI schemes, there was a headlong rush by many local authorities around the UK to enter into pilot schemes to test the water.

Islington PFI being one of the first in London to do so and Camden soon following close behind; there were discussions and meetings between Islington and Camden to explore common ground issues.

Whereas Islington PFI ventured a radical approach to outsource not only the construction and maintenance but also the day to day management of the social housing stock, Camden PFI on the other hand elected a more conservative approach of retaining full control of management of the housing stock and only outsourcing the “major refurbishment and maintenance” aspects to a PFI scheme.

The “Chalcots” was selected as being prime for the PFI pilot, due to the fact that the property was largely untouched and not re-furbished since being built in the period of 1965 to 1968.

The Chalcots historically comprised Dorney, Bray, Burnham and Taplow and was originally designed and built by the same group of property developers as the other Chalcots “town houses” which have always been private. It had been the original intention that the four “towers” would be luxury apartments with only three “large” apartments per floor.

However, during the building phase of these properties the “Ronan Point” collapse disaster happened 16th May 1968, concrete high rise become a dirty word and the “luxury” high rise funding went pear shape. Camden on the other hand was crying out for more housing stock and was offered to take the four “towers” over with minor conversions being conducted to the original three apartments per floor to the current seven properties per floor, made up of “two” three beds, “three” two beds, “one” one bed and “one” studio flat.

Blashford on the other hand was always conceived and built by the local authority and was not originally part of the “Chalcots” estate at all, only later was it appendaged onto the Chalcots “four” to become the Chalcots “five”

This therefore, is a quick summary of the history of the Chaclots estate.

PFI experience so far on the Chalcots

PFI started in early 2006, with the creation of PFIC (Partners For Improvement in Camden Ltd) Notice the similarity to PFI which many people mistakenly believed stands for PFI in Camden which is true except that Partners is a different beast all together to “pure” PFI.

The difference is in the small print. Partners have at its centre an executive management where Camden (the local authority) is ONLY the client.

In essence the concept is to outsource all refurbishment and property maintenance for the next 15 years of the scheme. Within the business contract agreements Camden the local authority approved an “output specification” which is the main driver for the project for the next 15 years.

Output specification

Before moving on any further it is important to understand exactly what “output specification” is and what it means for the every day lives of the residents of the Chalcots.

In simple terms the client has stipulated that all social housing stock is to be brought up to a standard consistent with the “decent homes” guidelines. How the principal partner contractor achieves that is a matter for the contractor to sort out using a combination of “best practice” and “value for money”

Herein is the first “key” problem, which is loss of control for the local authority, since in all cases that have been examined so far with resident property works related issues have all, centred on this lack of control.

However, due to the very large size of this PFI project (around £150 millions over the 15 year contract) an Independent Certifier (IC) has been commissioned.

Naturally, most people both at the local authority and the residents were made to understand that the principle role of the IC was to “check” and “pass” as fit all said works in a process what has come to be known as “signing off” a property.

Role of the Independent Certifier (IC)

Herein is the second “key” problem, this time born out of a “total” misapprehension of the role of the IC process and more importantly what the IC was commissioned to achieve on the “Chalcots” PFI.

So what went wrong here in this fundamental miscommunication that persisted for more than “one” year and the entirety of the “Dorney” episode.

It was assumed that the IC when inspecting properties checks quality of finished product, compliance to known building regulations, known H&S issues and adherence to the submitted building plan. Whether knowingly or unwittingly this understanding persisted for one year.

The reality is rather different, the true and principle function of the IC is to inspect around 10% of all properties to make sure that the delivered components such as new windows, central heating, kitchen, bathroom and toilet fixtures are in place to sign off the property on this basis for the release of what is known within the local authority finance circles as a “unitary charge”

In other words the IC is acting as a broker between the “Bank” of the PFIC and the principle contractor to receive its funding in a timely fashion but not before the said work is completed.

Completion and the “sign-off” stage of a property are the next issue that will be discussed.

Sign-off and snagging

What is sign-off if it does not refer to a completed product?
Herein is the third “key” problem, when is a property complete if not at the IC stage. This brings us to snagging.

It is normally understood that snagging is a part of the construction and building cycle. It is expected that when a rebuild of a property is undertaken such as installation of new windows, central heating, kitchen, bathroom and toilet that snagging will pick up faults that occur after sign-off that went undetected, that could not reasonably have been foreseen.

However, experience has shown on the Chalcots especially at Dorney, which has been signed-off that this is not the case.

It is demonstrably seen to be in fact standard practice to only install all said components of the re-build into a property seek an early sign-off and then deal with all commissioning and testing to final finish in the “snagging” stage.

Motivations

It is known that sign-off generates real money in the form of the unitary charge release (which has been estimated to be on average around £80,000 per unit tenant property, less for leaseholds), clearly it serves the principle contractor well to bank this money fast. 10 to 15 flats alone will generate nearly £1 millions and the daily bank interest yields here are considerable.

The construction phase accounts for nearly half of the £150 millions PFIC project the remaining half is for the maintenance part going up to the end point of the 15 year contract.

By allowing lots of sub-standard properties to be released (signed-off) means that more of this precious maintenance fund will be used at a “faster” burn rate into the early years of the maintenance cycle of the contract.

Therefore, there is a high probability and risk that the monies will run out well ahead of the 15 year contract (the phrase do it fast and get out fast has been in common day use by a multitude of people involved in this project).

Summary

Three main problem areas so far highlighted are;

1. Output Specification
2. Role of the Independent Certifier (IC)
3. Sign-off and snagging

Only the misapprehension of the role of the IC has now been addressed by direct communication to all at a recent Operational Meeting (OPFOR).

It is hoped that with the correct levels of “direct” management pressure will the other issues be addressed too.

Originally published by Nigel RUMBLE on 4th July 2008