Tuesday, 2 December 2008

PFI at Chalcots - Third block due to complete


Bray, the third of the five blocks making up the Chalcots estate is due to be signed off by the Independent Certifier (IC) 19th December.

However, problems still remain in resident’s homes, such as leaking radiators, faulty windows and poorly regulated central heating controls, despite the IC sign off process. All the remaining problems will be transferred to the "snagging" process.

Security remains a "key" concern of the residents at Bray and indeed the whole of the Chalcots.

Inadequate lighting and no provision of a canopy to the entranceways continue to be a BIG concern for all residents.